Glanbia Project Topaz

Client Glanbia

Consultant PM Group

Start Date April 2018

Finish Date April 2019

Project Topaz consisted of a new 7.5t/hour drying process expansion of the Glanbia Ireland Belview facility, in order to increase capacity, a new third drier was added at the Belview plant.

The overall expansion project encompassed new:

  • Milk intakes;
  • Pasteurisers;
  • Evaporation facilities;
  • Drying facilities;
  • Bagging facilities

Suir Engineering’s scope of work included the complete electrical installation within the facility of the following systems:

Medium Voltage Installation, Low Voltage Installation, Installation of MCC’s & Low Voltage Switchgear, Sub-Mains Cabling, Ladders / Trays / Panelboards, Low Voltage General Services, Process Power, HVAC Power, Earthing & Lightning Protection, Lighting & Emergency Lighting, Fire Alarm, Security, External Lighting, Public Address, Voice & Data, I&C Containment & Support Process, Generator Installation, UPS Installation and Power Factor Correction