Skip to content

Keppel Project 20 Expansion & Upgrade

Client Keppel Data Centres

Consultant CBRE

Start Date March 2018

Finish Date December 2019

Project Description:The project was driven by a need to upgrade the existing infrastructure to meet the needs of Keppel Data Centres for the next 15yrs+. Works are designed and planned to replace legacy and inefficient M&E systems and to offer enhanced availability. Works were conducted in a live data centre environment.

The main elements of the works include MV Upgrade; LV Upgrade; Generator and Associated Fuel Transfer system; Cooling Upgrade; UPS Upgrade; BMS Upgrade; Fire Alarm and Emergency Lighting Upgrade; and Building & Ancillary works associated with the above upgrades